Multiple Choice
A complex project that is managed using a top-down,bottom-up approach to network diagrams means that:
A) management's top-down portion of the network contains the greatest detail.
B) top management does not have a basis for understanding the actual development of the project.
C) the top tier summary network does not give top management the basis for understanding the actual development of the project.
D) the bottom level information cannot be understood by those performing the actual work.
Correct Answer:

Verified
Correct Answer:
Verified
Q50: Dummy activities are used in AOA networks
Q75: Use the Gantt chart and activity list
Q76: Use the information in the table (all
Q77: The critical path of this network is:
Q78: The fastest completion time for this project
Q79: A project has the activity duration and
Q81: Which of the activities in the diagram
Q83: The AOA network described by this table
Q84: The three principal methods for accelerating project
Q85: An AOA network:<br>A)cannot show a merge activity.<br>B)cannot