Question 87

Multiple Choice

Scarlett Company has a direct material standard of 3 gallons of input at a cost of $5 per gallon. During July, Scarlett Company purchased and used 7,500 gallons. The direct material quantity variance was $750 unfavorable and the direct material price variance was $3,000 favorable. What price per gallon was paid for the purchases?


A) $5.00
B) $5.40
C) $4.60
D) $2.50

Correct Answer: