Job A3B Was Ordered by a Customer on September 25

Question 1

Multiple Choice

Job A3B was ordered by a customer on September 25.During the month of September,Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor.The job was not finished by the end of the month,but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October.The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred.What is the balance in the Work in Process account at the end of September relative to Job A3B?


A) $5,500
B) $11,500
C) $6,500
D) $9,500
E) $14,500