Multiple Choice
Exhibit 18-1 In 2010, Alpha Construction began work on a contract with a price of $850, 000 and estimated costs of $595, 000.Data for each year of the contract are as follows:
- Refer to Exhibit 18-1.Under the percentage-of-completion method of revenue recognition, gross profit in 2010 would be
A) $102, 000
B) $260, 000
C) $255, 000
D) $425, 000
Correct Answer:

Verified
Correct Answer:
Verified