Exhibit 18-2 The following information relates to a project of the Sarasota Construction Company:
201020112012 Construction costs incurred $136,000$546,500$200,000 Estimated costs to complete 714,000227,500\begin{array}{llll}&2010&2011&2012\\\text { Construction costs incurred } & \$ 136,000 & \$ 546,500 & \$ 200,000 \\\text { Estimated costs to complete } & 714,000 & 227,500 & --\end{array}
The contract price was $1, 000, 000.Sarasota used the percentage-of-completion method of revenue recognition.
-
Refer to Exhibit 18-2.What amount of gross profit was recognized in 2010?


A) $150, 000
B) $ 28, 571
C) $ 24, 000
D) $ 20, 400