Question 19

Multiple Choice

Choose, among the following options, the inputs for Capacity requirements planning (CRP) .
1) Loading capacity
2) Rescheduling data from MPS
3) Routing data
4) Planned and released order from MRP systems


A) (1)
B) (2) and (3)
C) (1) , (3) and (4)
D) (4)

Correct Answer: