Dave Is Conducting Rough-Cut Capacity Planning (RCCP)for a Product GTB

Question 17

Multiple Choice

Dave is conducting Rough-Cut Capacity Planning (RCCP) for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.
Dave is conducting Rough-Cut Capacity Planning (RCCP) for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.   A)  WC1: 1.2 hours WC2: 3.6 hours WC3: 5.6 hours B)  WC1: 2.2 hours WC2: 3.1 hours WC3: 3.6 hours C)  WC1: 1.2 hours WC2: 3.1 hours WC3: 1.2 hours D)  WC1: 5.2 hours WC2: 1.2 hours WC3: 5.6 hours


A) WC1: 1.2 hours WC2: 3.6 hours WC3: 5.6 hours
B) WC1: 2.2 hours WC2: 3.1 hours WC3: 3.6 hours
C) WC1: 1.2 hours WC2: 3.1 hours WC3: 1.2 hours
D) WC1: 5.2 hours WC2: 1.2 hours WC3: 5.6 hours