Multiple Choice
Dave is conducting Rough-Cut Capacity Planning (RCCP) for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.
A) WC1: 1.2 hours WC2: 3.6 hours WC3: 5.6 hours
B) WC1: 2.2 hours WC2: 3.1 hours WC3: 3.6 hours
C) WC1: 1.2 hours WC2: 3.1 hours WC3: 1.2 hours
D) WC1: 5.2 hours WC2: 1.2 hours WC3: 5.6 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Material Requirements Planning (MRP)operates on a component
Q13: There are 3 work stations (WC)with the
Q14: Capacity is the measure of productive capability
Q15: What is the planning horizon of the
Q16: Of the following capacity planning horizons, which
Q18: Product gamma requires a sequence of
Q19: Choose, among the following options, the inputs
Q20: Using RCOF and the information in
Q21: Capacity Requirements Planning (CRP)is a Capacity planning
Q22: Product gamma requires a sequence of 5