Generally, there are 7well known hidden costs of outsourcing.Find these costs among the possible choices.Which of the following is not considered one of the 7 hidden cost of outsourcing?
1) Transportation costs
2) Quality costs
3) Internal Coordination costs
4) Supply Chain Risk Management costs
A) (2)
B) (1) and (4)
C) (2) , (3) , and (4)
D) None of the above