Multiple Choice
What is the buyer's risk when the probability of outsourced function being disrupted is 2% and the cost of a disruption is $4,000,000?
A) $500,500
B) $250,000
C) $80,000
D) $100,000
Correct Answer:

Verified
Correct Answer:
Verified