Essay
Hemo-tech, Inc., a biomedical technology and research laboratory, produces a standard blood filtering device on an assembly line basis. Six basic tasks are performed along an assembly line. The time to perform each task and the tasks that must immediately precede each task are in the table below. Twenty pumps per 450-minute day must be produced by the assembly line.
a. Draw the network diagram of the precedence relationships.
b. Identify the absolute minimum and maximum cycle times.
c. How many workstations are required to meet the schedule?
d. What is the cycle time required to meet demand?
e. Balance this line using most following tasks heuristic.
f. What is the efficiency of the line obtained in part e?
g. Can the efficiency of this solution be improved? Explain.
Correct Answer:

Verified
(a) The appropriate diagram appears belo...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q6: Job lots are groups or batches of
Q41: Takt time is<br>A) the total work time
Q61: Which of the following is not one
Q74: Briefly explain what "slotting" is. Why is
Q87: Which of the statements below best describes
Q125: Brandon's computer shop has hired a consultant
Q151: A production line is to be designed
Q162: The work cell improves process layouts by
Q167: Which of the following is true of
Q170: Because problems with fixed-position layouts are so