Essay
An assembly line with 11 tasks is to be balanced. The longest task is 2.5 minutes, the shortest task is 0.5 minutes, and the sum of the task times is 20 minutes. The line will operate for 700 minutes per day.
a. Determine the minimum and maximum cycle times.
b. What range of output is theoretically possible for the line?
c. What is the minimum number of stations needed if the maximum output rate is to be sought?
d. What cycle time will provide an output rate of 200 units per day?
Correct Answer:

Verified
Minimum cycle time is 2.5 minutes. Maxim...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: You have been asked to balance
Q7: "Having a focused work centre is like
Q12: A work cell is required to make
Q13: The major problem addressed by the warehouse
Q14: Cross-docking is<br>A) seldom placing an item in
Q22: Retail layouts thrive on the notion that<br>A)
Q31: Process-oriented layouts typically have low levels of
Q44: The _ is a non-numeric method for
Q122: What are the two basic types of
Q129: What are the advantages and disadvantages of