Essay
A work cell is scheduled to build 150 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theatre projection systems. The work cell has 8 hours of productive work each day, five days per week. What is takt time for this cell?
Correct Answer:

Verified
The cell has 8 × 5 = 40 hours ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q15: An assembly line with 11 tasks is
Q29: Define the following terms that occur in
Q56: Assembly line balancing has just been used
Q88: An assembly line with 11 tasks is
Q93: The dominant problem associated with the fixed-position
Q94: A work cell is scheduled to build
Q95: The main advantage of a product-oriented layout
Q97: For which of the following operations would
Q134: Solving a load-distance problem for a process-oriented
Q139: Which of the following layouts generally has