Essay
A work cell is scheduled to build 250 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theatre projection systems. The work cell has 16 hours of productive work each day, seven days per week. What is takt time for this cell?
Correct Answer:

Verified
The cell has 16 × 7 = 112 hour...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: In assembly-line balancing, cycle time (the ratio
Q19: In assembly-line balancing,the theoretical minimum number of
Q29: Define the following terms that occur in
Q56: Assembly line balancing has just been used
Q66: To develop a good facility layout, what
Q91: A work cell is scheduled to build
Q93: The dominant problem associated with the fixed-position
Q95: The main advantage of a product-oriented layout
Q97: For which of the following operations would
Q139: Which of the following layouts generally has