Multiple Choice
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut three days from the project's duration, activity ________ should be crashed, adding ________ to the total project cost.
A) D; $2,000
B) D; $1,000
C) E; $500
D) E; $1,000
E) E; $1,500