A work centre had actual input of 280 hours and actual output of 270 hours. What is the change in backlog?


A) 10
B) -10
C) 0
D) 1.037
E) unable to determine with given information

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: What does Johnson's rule do?

Q32: A work centre is interested in limiting

Q33: The word "infinite" in infinite capacity scheduling

Q36: Complete the table, find average lateness,

Q39: Five jobs are waiting for processing

Q42: A firm that specializes in desktop

Q77: The benefits of effective scheduling include lower

Q88: Which of the following is not tracked

Q98: What is the primary disadvantage of the

Q136: Describe finite capacity scheduling in a sentence

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines