Multiple Choice
A work centre is interested in limiting work-in-process by not allowing production to start again until the current batch is finished. The best solution most likely involves
A) MRP.
B) ConWIP cards.
C) Gantt Charts.
D) Johnson's rule.
E) Loading.
Correct Answer:

Verified
Correct Answer:
Verified