Given the following chart of jobs assigned with Johnson's rule suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc). Suppose job B is divided into jobs B1 and B2, each with a body work time of 4.5 hours and a paint time of 2 hours. How much is makespan reduced by this splitting of B?
Correct Answer:

Verified
B1 could start on paint at time = 34.5 (...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: At Morgan's Transformer Rebuilding, a set
Q5: Air Canada uses mathematical short-term scheduling techniques
Q7: Use Johnson's rule to determine the
Q8: A manufacturer has the following jobs
Q9: Three jobs are to be assigned
Q11: The following jobs are waiting to
Q32: A practitioner of family medicine begins her
Q59: When a set of jobs must pass
Q120: Explain, in your own words, how backward
Q127: In repetitive manufacturing, what are the advantages