Multiple Choice
Capacity planning in closed-loop MRP
A) utilizes feedback about workload from each work centre.
B) may make use of resource requirements profiles (load reports) .
C) may smooth work centre loads with such tactics as overlapping and lot splitting.
D) does not add capacity, but rather seeks effective use of existing capacity.
E) All of the above are true.
Correct Answer:

Verified
Correct Answer:
Verified