Essay
Consider the following bill of material. Forty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material.
Correct Answer:

Verified
Item A: 40 units; Item B: 40 × 2 = 80 un...View Answer