Multiple Choice
The extension of MRP which extends to resources such as labour hours and machine hours, as well as to order entry, purchasing, and direct interface with customers and suppliers is
A) MRP II.
B) enterprise resource planning.
C) the master production schedule.
D) closed-loop MRP.
E) not yet technically possible.