Multiple Choice
Distribution resource planning (DRP) is
A) a transportation plan to ship materials to warehouses.
B) a time-phased stock replenishment plan for all levels of a distribution network.
C) a shipping plan from a central warehouse to retail warehouses.
D) material requirements planning with feedback loop from distribution centres.
E) a material requirements planning package used exclusively by warehouses.
Correct Answer: