Multiple Choice
If the following jobs are sequenced according to the SLACK rule,then the total number of jobs that would be late is (assume zero for today's date)
A) 1 jobs.
B) 2 jobs.
C) 3 jobs.
D) 4 jobs.
Correct Answer:

Verified
Correct Answer:
Verified