As Part of Its Quality-Improvement Program,a Company Is Conducting a Time

Question 1

Multiple Choice

As part of its quality-improvement program,a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element: As part of its quality-improvement program,a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element:   The standard time for this job using an allowance factor of 16% is A) 1.809 minutes. B) 2.098 minutes. C) 1.530 minutes. D) 2.233 minutes. The standard time for this job using an allowance factor of 16% is


A) 1.809 minutes.
B) 2.098 minutes.
C) 1.530 minutes.
D) 2.233 minutes.

Correct Answer:

verifed

Verified