Multiple Choice
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. What is the earliest completion of the project diagrammed?
A) 23 weeks
B) 24 weeks
C) 28 weeks
D) 37 weeks
Correct Answer:

Verified
Correct Answer:
Verified