Colson Corp.has planned a simple project with four tasks.The task information for the project is shown below: Does any task have slack? If so,how much?
A) None of the tasks have slack.
B) Task B has three days of slack.
C) Task C has four days of slack.
D) Task D has two days of slack.
E) Task C has three days of slack.
Correct Answer:

Verified
Correct Answer:
Verified