Joe Jones is a project manager on a major installation.He has been asked to provide weekly status reports on the project schedule.Joe should consider using which of the following?
A) Gantt chart
B) Crashing reports
C) WBS report
D) Network diagram
Correct Answer:

Verified
Correct Answer:
Verified