Multiple Choice
Significant changes in an MPS quantity several weeks into the planning horizon can:
A) Make the MRP more accurate.
B) Cause inconsistencies in the MRP.
C) Reduce stockouts.
D) Increase safety stock.
Correct Answer:

Verified
Correct Answer:
Verified