Question 1
Multiple Choice
A master production schedule shows the beginning inventory is 50 units,the forecast is 200 units,and actual customer orders are 220 units.What is the quantity that is available to promise in period 1?
Question 2
Multiple Choice
The following table shows capacity requirements data for making tabletops.
Which of the following is TRUE?
Question 3
Multiple Choice
A master production schedule shows the following information:
Using a lot-for-lot rule,what is the MPS quantity for period 1?
Question 4
Multiple Choice
The following table shows capacity requirements data for making Blodgetts.
A load profile would show:
Question 5
Multiple Choice
Distribution requirements planning:
Question 6
Multiple Choice
Which of the following would benefit the most from MRP?
Question 7
Multiple Choice
Advanced planning and scheduling systems:
Question 8
Multiple Choice
A master production schedule shows the beginning inventory is 100 units,the forecast is 250 units,and actual customer orders are 400 units.Using a lot-for-lot rule,what is the MPS quantity for period 1?
Question 9
Multiple Choice
MRP is a process that would be most applicable in which situation?
Question 10
Multiple Choice
The primary purpose of an MRP system is to:
Question 11
Multiple Choice
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers.The type of system Zanda should consider is known as:
Question 12
Multiple Choice
Which of the following is NOT an input to an MRP system?
Question 13
Multiple Choice
Which of the following pieces of information is NOT contained in an MRP secondary report?
Question 14
Multiple Choice
All of the following are outputs from an MRP system EXCEPT:
Question 15
Multiple Choice
If the cumulative lead time is eight weeks,for a project to be feasible the MPS planning horizon must be:
Question 16
Multiple Choice
A master production schedule shows the beginning inventory is 50 units,the forecast is 80 units,and actual customer orders are 70 units.Using a lot-for-lot rule,what is the MPS quantity for period 1?