Multiple Choice
Distribution requirements planning:
A) Uses logic that starts at the manufacturing plant and works forward toward the customer.
B) Includes only firm orders in its calculations.
C) Uses logic similar to MRP,beginning at the point closest to the customer.
D) Is normally not included as a module in ERP software.
Correct Answer:

Verified
Correct Answer:
Verified