Multiple Choice
A company must make 800 units per day.The company has two eight-hour shifts.What is the efficiency if the total time to complete all tasks is 11 minutes and the company is using 15 workstations?
A) 94 percent
B) 33 percent
C) 83 percent
D) 61 percent
Correct Answer:

Verified
Correct Answer: