Multiple Choice
Making all product release deadlines imminent:
A) creates too much programmer stress and should be avoided if at all possible.
B) pushes a realistic expectation for completion to the fore.
C) usually results in minimally functional software.
D) actually slows down project development because of numerous avoidable errors.
Correct Answer:

Verified