    The Longest Path Through a PERT Diagram Is Referred to as the ________
Solved

The Longest Path Through a PERT Diagram Is Referred to as the ________

Question 1

Question 1

Multiple Choice

The longest path through a PERT diagram is referred to as the ________ path.


A) critical
B) hardest
C) fastest
D) slowest

Correct Answer:

verifed

Verified

Related Questions

Q2: List four criteria for evaluating computer hardware

Q3: _ is used to determine the point

Q4: Systems analysts formulate numbers that represent both

Q5: Using a weighted average formula to determine

Q6: Changes in employee behavior such as unusually

Q7: The main advantage of the PERT diagram

Q8: Which of the following is not an

Q9: PERT diagrams occasionally need to use dummy

Q10: Which of the following is not a

Q11: Which of following is not a specific

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines