Multiple Choice
The difference between the actual quantity and the standard quantity,multiplied by the standard price,is the:
A) direct materials spending variance.
B) direct materials volume variance.
C) direct materials price variance.
D) direct materials quantity variance.
Correct Answer:

Verified
Correct Answer: