Multiple Choice
Swan Company has a direct labor standard of 15 hours per unit of output.Each employee has a standard wage rate of $14 per hour.During March,employees worked 13,100 hours.The direct labor rate variance was $9,170 favorable,and the direct labor efficiency variance was $15,400 unfavorable.What was the actual payroll?
A) $183,400
B) $168,000
C) $174,230
D) $192,570
Correct Answer:

Verified
Correct Answer:
Verified
Q107: Exeter has a materials standard of 1
Q108: A spending variance is made up of:<br>A)volume
Q109: Warner Co.has budgeted fixed overhead of $150,000.Practical
Q110: Cascade Inc.has provided the following information:<br> <img
Q111: Comparing the master budget with the flexible
Q113: Who would typically be responsible for the
Q114: The difference between the actual quantity and
Q115: The standard labor rate is:<br>A)the expected hourly
Q116: A quantity standard is the amount of
Q117: Easily attainable standards are the best for