Keith assembles peanut valves and the recorded data is displayed in the table.What is the select time for this job element if he is rated at 75%?
A) Greater than or equal to 3 minutes
B) Less than 3 minutes but greater than or equal to 2.7 minutes
C) Less than 2.7 minutes but greater than or equal to 2.4 minutes
D) Less than 2.4 minutes
Correct Answer:

Verified
Correct Answer: