Solved

Table 41
the Union Manufacturing Company Is Producing Two Types of of Products

Question 117

Multiple Choice

Table 4.1
The Union Manufacturing Company is producing two types of products: A and B.
The demand forecasts, batch size, and time standards follow:
 Product A  Product B  Demand forecast (units/yr)  10004000 Batch size (units/batch)  2010 Processing time (hr/unit)  3.24.5 Setup time (hr/batch 020\begin{array} { l | c | c } & \text { Product A } & \text { Product B } \\\hline \text { Demand forecast (units/yr) } & 1000 & 4000 \\\text { Batch size (units/batch) } & 20 & 10 \\\text { Processing time (hr/unit) } & 3.2 & 4.5 \\\text { Setup time (hr/batch } & 0 & 20\end{array}
Both products are produced at the same operation called Mark I.
-Using Table 4.1,what is the total number of hours required of Mark I equipment for the next year?


A) less than 29,000 hours
B) between 29,000 and 30,000 hours
C) between 30,000 and 31,000 hours
D) more than 31,000 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions