Multiple Choice
Table 4.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 4.2,what is the minimum number of machines needed (assuming no reliance on short-term options) ?
A) less than or equal to 22
B) more than 22 but less than or equal to 25
C) more than 25 but less than or equal to 28
D) more than 28
Correct Answer:

Verified
Correct Answer:
Verified
Q5: _ is the degree to which equipment,
Q6: Within a process, what is a bottleneck?
Q31: Define each of the following capacity strategies:
Q85: A(n) _ is an operation that has
Q117: Table 4.1<br>The Union Manufacturing Company is
Q119: Which one of the following statements concerning
Q121: Sleep Tight Motel has the opportunity
Q123: The Union Manufacturing Company is producing
Q124: Up,Up & Away is a producer
Q131: In a tire manufacturing plant, measuring capacity