Multiple Choice
Table 3.5
-Using Table 3.5,how many weeks can activity B be delayed without changing the whole project's earliest completion time?
A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
Correct Answer:

Verified
Correct Answer:
Verified