Time (Days) -Using Table 3

Question 124

Multiple Choice

Table 3.2
Time (days)
 Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 246 B 147 C  A 222 D  B 1710 E  D 246 F  E 123 G  C 3417 H  D, G 3711 I  D 8910 J  F,H 456 K  I 111\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & \cdots & 2 & 4 & 6 \\\text { B } & \cdots & 1 & 4 & 7 \\\text { C } & \text { A } & 2 & 2 & 2 \\\text { D } & \text { B } & 1 & 7 & 10 \\\text { E } & \text { D } & 2 & 4 & 6 \\\text { F } & \text { E } & 1 & 2 & 3 \\\text { G } & \text { C } & 3 & 4 & 17 \\\text { H } & \text { D, G } & 3 & 7 & 11 \\\text { I } & \text { D } & 8 & 9 & 10 \\\text { J } & \text { F,H } & 4 & 5 & 6 \\\text { K } & \text { I } & 1 & 1 & 1 \\\hline\end{array}
-Using Table 3.2,what is the earliest expected time of completion of the whole project?


A) less than or equal to 21 days
B) greater than 21 but less than or equal to 22 days
C) greater than 22 but less than or equal to 23 days
D) greater than 23 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions