Multiple Choice
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,if the expected time for activity E is changed to 9 weeks,by how many weeks will the projects expected completion time increase?
A) It will not change.
B) It will increase by 1 week.
C) It will increase by 2 weeks.
D) It will increase by 3 or more weeks.
Correct Answer:

Verified
Correct Answer:
Verified