Multiple Choice
The difference between the earliest start (ES) and the earliest finish (EF) times for any activity in a project network is the
A) activity total slack time.
B) activity free slack time.
C) estimated duration of the activity.
D) latest finish time for the activity.
Correct Answer:

Verified
Correct Answer:
Verified