Multiple Choice
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,what is the probability that the project will take 16 or more weeks to complete? You will need to refer to a standard normal table to answer the question.
A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Which one of the following best describes
Q28: What characteristics should project manager possess?
Q55: Risk is a measure of the probability
Q63: Table 3.12<br>You are responsible for managing
Q64: To calculate the probability of completing a
Q66: What are the benefits of using CPM/PERT?
Q70: Table 3.3<br> <span class="ql-formula" data-value="\begin{array}
Q83: Projects cannot have more than one critical
Q85: The optimistic time is the probable time
Q91: When using the beta distribution for estimating