Multiple Choice
Table 3.3
-Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?
A) 1 activity
B) 2 activities
C) 3 activities
D) 4 or more activities
Correct Answer:

Verified
Correct Answer:
Verified