Multiple Choice
Table 3.11
You are responsible for managing a project with the
following activities (times are given in days) .
-Using,Table 3.11,which of the following activities has the largest amount of slack?
A) Activity B
B) Activity D
C) Activity E
D) Activity F
Correct Answer:

Verified
Correct Answer:
Verified