Multiple Choice
Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.12,if the expected time for activity D is increased to 6 weeks,by how many weeks will the project's expected completion time increase?
A) It will not increase.
B) It will increase by 1 week.
C) It will increase by 2 weeks.
D) It will increase by more than 2 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Table 3.8<br> <span class="ql-formula" data-value="\begin{array}
Q14: Network methods let project managers analyze the
Q16: When using the beta probability distribution to
Q18: Draw the network corresponding to the
Q20: _ is a measure of the probability
Q57: Of the four major phases in project
Q62: Total slack can be calculated as the
Q77: Identify and briefly explain the four categories
Q107: What are the five steps involved in
Q108: A project is an interrelated set of