Question 18

Essay

Draw the network corresponding to the following information.Also,complete the table,identify the critical path,and specify project completion time.
 Activity  Immediate  Predecessor(s)  Time  (Weeks)  A 3 B 4 C  A 6 D  B 9 E  B 6 F  C,D 6 G D,E8HG,F9\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (Weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\hline \text { B } & \cdots & 4 \\\hline \text { C } & \text { A } & 6 \\\hline \text { D } & \text { B } & 9 \\\hline \text { E } & \text { B } & 6 \\\hline \text { F } & \text { C,D } & 6 \\\hline \text { G } & \mathrm { D } , \mathrm { E } & 8 \\\hline \mathrm { H } & \mathrm { G } , \mathrm { F } & 9 \\\hline\end{array}
 Activity  Earliest  Start  Earliest  Finish  Latest  Start  Latest  Finish  Slack ABCDEFGH\begin{array} { | c | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Earliest } \\\text { Start }\end{array} & \begin{array} { c } \text { Earliest } \\\text { Finish }\end{array} & \begin{array} { c } \text { Latest } \\\text { Start }\end{array} & \begin{array} { c } \text { Latest } \\\text { Finish }\end{array} & \text { Slack } \\\hline \mathrm { A } & & & & & \\\hline \mathrm { B } & & & & & \\\hline \mathrm { C } & & & & & \\\hline \mathrm { D } & & & & & \\\hline \mathrm { E } & & & & & \\\hline \mathrm { F } & & & & & \\\hline \mathrm { G } & & & & & \\\hline \mathrm { H } & & & & & \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | c | c | ...