Consider the Tasks,durations,and Predecessor Relationships in the Following Network AWhat Is the Expected Time for Activity B?
B
Essay
Consider the tasks,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow.
a.What is the expected time for activity B?
b.What is the variance for activity B?
c.Based on the calculation of estimated times,what is the critical path?
d.What is the estimated time of the critical path?
e.What is the activity variance along the critical path?
f.What is the probability of completion of the project before week 42? You will need to refer to a standard normal table to answer the question.
Correct Answer:

Verified
Network diagram is below.
a.
Weeks
b. ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
a.
b. ...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q17: Typically activities along the critical path have
Q19: Resource allocation is an attempt to reduce
Q40: A(n) _ chart is a project schedule
Q70: Projects often cut across organizational lines.
Q83: In a network diagram,an "activity"<br>A) is the
Q88: The _ cost refers to the additional
Q90: Before beginning to create a PERT/CPM network
Q91: If one activity along the critical path
Q104: Many small incremental changes to project objectives,
Q120: Why do managers want to know the