Multiple Choice
Before beginning to create a PERT/CPM network model for a project,the project must be described in general terms.Two types of information that must be defined are
A) slack time and activities.
B) manpower allocation and project due date.
C) crash times and manpower allocation.
D) activities and precedence relationships.