Multiple Choice
Fun Vehicles,Inc.,makes "beach buggies" on an assembly line with 11 work elements.Information on these work elements is as follows:
The company wants to re-balance its line to increase the output to two buggies every three minutes.Use the longest work-element time rule to assign tasks to the workstations.Which of the following is the assignment for the first two stations (S1 and S2) produced by this rule?
Station Station
1 Tasks 2 Tasks
A) 1, 2 3, 4, 5
B) 1, 2 4, 6, 3, 9
C) 1, 4 3, 2, 5
D) 1, 3, 4 2, 5, 8
Correct Answer:

Verified
Correct Answer:
Verified
Q24: A(n) _ allocates space and indicates placement
Q37: Malhotra Company has four distribution centers
Q39: Given the following data about an
Q40: Table 9.15<br>Balance the following line for
Q41: A product layout generally has slower processing
Q45: Table 9.2<br>Durham Toy, Inc. has five
Q46: Table 9.6<br>Nuts-and-Bolts Inc. wishes to find
Q69: Explain the concept of critical mass as
Q100: A product layout is best for low-
Q165: When outbound transportation costs are a dominant