Multiple Choice
Table 9.15
Balance the following line for an output rate of 3 units per minute,
using the longest work-element time rule.
-Use the information in Table 9.15.What is the balance delay for your solution?
A) less than or equal to 15%
B) more than 15% but less than or equal to 25%
C) more than 25% but less than or equal to 35%
D) more than 35%
Correct Answer:

Verified
Correct Answer:
Verified